How to install plug-in solar panels: a step-by-step UK guide
30 August 2026 · Guide
One of the big appeals of plug-in solar is that you install it yourself. No MCS-certified installer, no scaffolding, no rewiring. This guide walks through the whole process for a typical 800W kit, from choosing a position to doing your legal notification.
Before you start
- Check your kit is a UK-market product with a 13A plug and UKCA/CE marking (BS 7671 Amendment 4 compliant).
- Plan the position: south-facing is best, with a clear sky view. South-east and south-west are fine. East or west loses roughly 10-20% of generation. Avoid shading from trees, chimneys and other buildings - even partial shading cuts output.
- Find your DNO by postcode (Energy Networks Association website) and bookmark their G98 notification form - you'll need it before you connect.
- Check your socket: the regulations require connection to a suitable socket, ideally an outdoor weatherproof socket (IP-rated). Do not use extension leads or coiled cable reels - the instruction manuals say this explicitly for safety.
Step 1: Mount the panels
Follow your kit's mounting instructions - they vary by product:
- Balcony kits (EcoFlow STREAM) use brackets for lattice, glass or concrete balconies. Fix them securely - panels are heavy (15-25kg each) and must survive UK winds.
- Ground kits use adjustable tilt frames. UKSOL's hybrid mount works on flat ground (add ballast) or a solid wall. Position at roughly 30-40° tilt for best year-round output.
- Wall mounting needs solid masonry - use the supplied hardware and make sure the fixings are rated for the weight.
Safety first: if you're working at height or the position feels unsafe, get a professional installer - the "no installer needed" rule is about certification, not about doing anything dangerous.
Step 2: Connect the panels to the microinverter
Plug the panels' DC cables into the microinverter using the MC4 connectors. Most kits are designed to be foolproof - connectors click in and lock. Keep the panel side unplugged until the system is fully assembled, and never work on connections in wet conditions.
Step 3: Plug into the socket
Connect the microinverter's cable to your outdoor socket. The system then:
- Checks the grid frequency and voltage
- Starts producing power when the sun is up
- Prioritises power for your home, exporting the surplus
Most kits have a status light and an app (EcoFlow, UKSOL, Anker all ship app monitoring). Give it a minute to boot, then check the app shows live generation.
Step 4: Notify your DNO (G98) - don't skip this
Under the G98 Engineering Recommendation, you must notify your Distribution Network Operator before connecting a small generation system. This is a fit-and-notify process:
- Fill in the free online form on your DNO's website (most have a dedicated small-scale generation page)
- You can connect immediately while the notification is processed - you don't need prior approval
- The DNO has 28 days to respond; most confirm much faster
Why it matters: a non-notified system can affect your home insurance and cause issues if you later sell the property. It takes minutes and costs nothing.
Step 5: Set up monitoring and enjoy
Install the app, connect the microinverter to your Wi-Fi, and you'll see live generation, daily totals and (on some kits) your self-consumption. Keep panels reasonably clean - an occasional rinse helps, and snow usually slides off tilted panels.
Common mistakes to avoid
- Using an extension lead or cable reel - explicitly warned against in every kit manual
- Importing a European kit with a Schuko plug - not compliant in the UK
- Blocking the panels with shade - a shaded 800W kit can generate less than a clear 400W kit
- Skipping the G98 notification - it's free and takes minutes, but the consequences of skipping are real
- Over-tightening balcony brackets - panels expand and contract; follow the torque guidance
If anything in the manual contradicts this guide, follow your kit's manual - it's specific to your product.